Smart Bylaws Guide – Case Studies – Koo's Corner
560-598 Hawks Avenue, Vancouver, BC
|
Features:
|
Brownfield in
residential neighbourhood
Conversion of
existing building
Infill
Higher
density ground oriented residential
Green
building technologies
|
|
|
50’ x
122’ = 0.057 Ha.
|
|
Residential
Units:
|
6 townhouses
(condominium). Two loft style, one 2-storey, three 2.5-storey.
720 – 1195
sq. ft. (average 925 sq. ft.)
|
|
Gross
Residential Density:
|
106 uph, 0.95
FSR
|
|
Commercial
Units:
|
|
|
Site
Coverage:
|
63.6%
|
|
Maximum
Height:
|
2.5 storeys
|
|
Parking:
|
5 – one in
the bottom of each of the five larger units
|
|
Pre-development
Usage:
|
Car repair
shop and parking
|
|
Selling
Price:
|
$185,000 to
$280,000
|
|
Strata Fees:
|
$65 to $90
per month
|
|
Date Completed:
|
September, 2002
|
|
Developer:
|
Chesterman
Property Group (Robert Brown) |
Project Overview
Koo’s Corner is an infill project of six
townhouses on a former brownfield site. The project is located
in a residential neighbourhood in Vancouver that is adjacent to
Chinatown and downtown, and across from a park. The
centerpiece is the integration of an existing building into the
project, coupled with a design that maintains the character of the
neighbourhood. The developer incorporated green building
features that made the units more marketable.
Land Use
The previous owner, who was also the adjacent
landowner, had used the site for decades as a car repair shop.
The developer approached the former owner, and after resolution of
site contamination issues, purchased the two 25-foot lots at Hawkes
and Keefer. The developer’s vision was to maximize the
density on the corner by orienting six townhouses across the two
lots.
The City granted the developer several
variances and approvals that differed from what was allowed under
the “by-right” zoning. These included:
- increased
density (under the Vancouver Charter legislation and RT-3
zoning, the City allows 0.75 FSR by right, and a
performance-based addition of 0.20 FSR (0.95 total FSR) that can
be earned for infill projects);
- relaxed
parking standards (exempting the smallest unit from requiring a
parking space);
- decreased
setbacks (from fifteen to five feet in what had been the front
yard setback on Keefer street);
- increased
height; and
- reduced
open space.
The location is close to shopping, transit,
services and local entertainment. One resident does not own a
car because of the location. The bus stop is a two-minute
walk away, and downtown is fifteen minutes by foot. Several
residents bike to work.
The building covers 63% of the site, with very
limited yard space that is supplemented by roof decks.
Residents use the narrow front yards because they are sunny and
across from the park while the backyards are too shady.
The project meets the City’s goals of
increasing residential densities while retaining neighbourhood
character and liveability. The RT-3 zoning encourages the
retention of neighbourhood and streetscape character, through the
renovation, and restoration of existing character buildings.
Design
The designer paid special attention to
integrating the townhouses into the neighbourhood and using the
existing 1940’s era building that was on site. Given the
high density for that site, careful attention was paid to design
details.
Green building features used in the project
include:
- Heat
Recovery Ventilators
- Solar
pre-heating of hot water
- Greywater
heat recovery
- Extensive
used of reclaimed materials
- Reduced
use of finishing materials
- Low
VOC finishes and adhesives
Community Process
The developer chose to resolve issues with the
neighbours and leaders in the community before formally entering the
City development process. This included delivering plans to
the immediate neighbours, seeking out the chair of the community
association, explaining green building principles, and providing
tours for neighbours around his most recent project in the City.
The neighbours were more concerned about design
than density. A tall bay window was added to the wall of the
end unit fronting on Keefer Street to break the visual barrier of
the building. A parking compromise was reached that exempted
the smallest unit from a required parking space, allowed rear land
access to parking for the two units in the converted building, and
provided half-buried garages for the three new townhouses accessed
by just two pavement cuts. Significant investment went into
the design of the garage doors.
The developer went beyond traditional
notification requirements and attempted to meet all of the
neighbours concerns.
“The developer suggests
that early, open neighbourhood consultation is vital with unusual
projects like this and that you have to be ready to listen to the
local residents and make concessions where necessary. In this case,
neighbours also appreciated the efforts Chesterman went to, to
develop a green building and this helped gain approvals. Brown
acknowledges the support and skill of the municipal planner who
helped navigate the complex urban design standards of the city.”
|
Costs and Affordability
Land
|
$70/buildable sq. ft.
|
Building
|
$125 /sq. ft.
|
Construction Soft Costs (e.g. taxes, DCCs, consultants)
|
$40 / sq. ft.
|
Infrastructure (paid by the developer)
|
$0
|
Total
|
$1.4 million
|
Conventional sources provided project financing
and the government did not supply any financial support. Costs
were higher than expected because of the detailed designs required
by the tight site and the extended approvals process.
Five out of six units were sold before the
project was completed. The project was marketed through word
of mouth, and several of the purchasers were interested in the green
building design features. Koo’s Corner is considered
relatively affordable for a new home in the most expensive housing
market in Canada.
City Support
The project planner worked hard to provide
advice that supported the project, and the Director of Planning
granted the higher density. The developer also had to obtain
development permits and undertake two Board of Variance hearing to
meet the detailed urban design guidelines under the RT-3 zone.
The requests for increased density, relaxed parking restrictions,
small setbacks, increased height and reduced open space made the
approvals process particularly complex and not possible without the
assistance of supportive City staff.
For more information
Developer: Robert Brown, Chesterman Properties
Tel: 604 678 9024
Email: robert@chestermangroup.com
Municipality: Scot Hein
Tel: 604 873 7003
Email: scot_hein@city.vancouver.bc.ca
Zoning: RT3 www.city.vancouver.bc.ca/commsvcs/BYLAWS/zoning/rt-3.pdf
|